As part of Risk Management Strategy, lets look at “What If” scenarios.
Possible reasons software development projects could stop
before their projected date of completion are:
·
There can be budget cuts
·
There can be a change in the project priority
·
The project may have gone over the approved
budget
·
The company may be taken over
Lets assume that there was a budget cut and what if the
project stopped at 60% of the effort/time? Let’s
compare Project W (Waterfall) with Project S ( Agile Scrum)
Project
W ( Pure Waterfall)
|
Project
S ( Agile-Scrum)
|
10% of effort/time in setting up and Project scope
|
10% of effort/time in setting up and Project scope
|
25% of effort/time is spend on analysis of the software product
|
80% of effort/time spent in analyzing, developing and testing product
increments that are delivered iteratively every sprint.
|
40% of effort/time is spent on development and system testing
|
10% of effort/time involved in setting up and scoping the project.
|
15% of effort/time in fixing defects and executing integration,
regression thro’ acceptance.
|
|
10% time spent to properly close the project.
|
If Waterfall Project W stopped working at say 60% of
effort/time spent, then only possibly 10% of the features would have been
delivered.
If Agile Scrum Project S stopped working at 60% of
effort/time spent, then a good amt of sprints are already delivered (probably
40%-50% of the product backlog features) to the customers.
If we compare the earned values between
the Pure Waterfall and Agile scrum,
Project
W ( Pure Waterfall)
|
Project
S ( Agile-Scrum)
|
0% of effort/time involved in setting up and scoping the project.
|
0% of effort/time involved in setting up and scoping the project.
|
10% of effort/time is spend on analysis and design documentation,
source code value of the software product
|
50% of effort/time spent in analyzing, developing and testing product
increments that are delivered iteratively in bi-weekly basis.
|
Completed testing Packaged software is worth 10% of the total value
|
Completed testing Packaged software is worth 50% of the total value
|